Construction includes:
- Making repairs to the concrete pavement
- Placing 3.75 inches of new asphalt pavement over WIS 29
- Removing 1.25 inches of the existing pavement on the ramps at the WIS 29 interchanges at WIS 73 North/County M and WIS 73 South/County T and placing 2.25 inches of new asphalt
- Replacing the expansion joints on the east- and westbound WIS 29 bridges over the Black River west of Withee
- Replacing all wing walls on a culvert carrying the Popple River under WIS 29 west of County D in Owen
- Replacing the northwest wing wall on a culvert between Thorp and Withee
- Cleaning culverts and ditches
- Replacing guardrail and pavement markings