WIS 124, Duncan Creek to Bridge Street

Chippewa County 

Project Overview – Updated

Construction in 2025 includes:

  • Removing a portion of the existing pavement and placing new asphalt pavement
  • Replacing storm sewer on Elm Street
  • Updating sidewalk curb ramps

Construction in 2026 includes:

  • Modifying traffic signals at Columbia Street, Grand Avenue, Central Street, Spring Street and River Street
    • This work originally was planned to be done in 2025, but it has been pushed to 2026 because of utility conflicts on River Street.