Project Overview
Construction includes the following from:
- Rock Creek Bridge to West Hunt Street in Greenwood:
- Remove 3.25 inches of existing asphalt and place 3.25 inches of new asphalt pavement
 - Replace curb ramps and make spot curb and gutter repairs
 - Replace guardrail
 - Place pavement markings
 
 - From West Hunt Street north to WIS 29 East:
- Remove 3.25 inches of the existing pavement and place 3.25 inches of new asphalt pavement
 - Replace cattle passes no longer in use with culvert pipes
 - Extend a box culvert north of Greenwood and replace the structure’s wing walls
 - Overlay the Popple River Bridge deck with concrete, repair the concrete surface on the bridge abutments, replace wing walls and repair scour
 - Clean or replace culverts
 - Clean ditches
 - Replace or adjust guardrail