Project Overview
Construction includes the following from:
- Butterworth Road to 16th Street:
- Remove 3¼ inches of existing pavement and overlay the roadway with 3¼ inches of hot-mix asphalt
- Replace deteriorated culverts
- Repair frost heaves
- 16th Street to 6th Street:
- Replace the pavement structure with 9 inches of Portland cement concrete pavement, 6 inches of base aggregate, 12 inches of granular subbase and underdrain pipe
- Replace storm sewer system, curb ramps, curb and gutter
- Replace sidewalk at curb ramps at spot locations
- Add a designated bike lane between the travel and parking lanes in each direction
- Remove and haul decorative lights to city yard for repainting and reinstall in landscaped medians
- Replace portions of the city water main in a separate tied project
- 6th Street to US 2:
- Replace Portland cement concrete and hot-mix asphalt pavement with 9 inches of Portland concrete cement pavement
- Expand existing landscaped medians and left-turn lanes, remove one through lane and add a designated bike lane in each direction
- Upgrade curb ramps at city street and trail crossings