County OO, Business 53 to WIS 124

Chippewa County 

Traffic Impacts

Construction will be staged to allow County OO to remain open for most of the project.

  • County OO will remain open to southbound traffic for the first two stages.
  • Northbound traffic will be detoured via Business 53.
  • Some side roads will be closed at times.
  • During the final stage of construction, County OO will be closed for up to five days from South Joles Parkway to its intersection with Business 53 and WIS 124, so work can be completed on the County OO southbound lane. Southbound traffic will be detoured via Business 53.
  • Access to businesses and homes along County OO will be maintained.
  • Construction won’t impact the trail that runs parallel to County OO.