Schedule and Traffic Impacts
Page last updated: July 11, 2025
Schedule: June 16 to Sept. 9, 2025
Anticipated work scheduled: Crews will begin with WIS 153 in Mosinee. Crews will:
- Continue the concrete culvert overlay on the west cell of box culvert
- Remove all unsound materials
- Clean surfaces
- Install reinforcements
Traffic impacts (the next 10 days):
- Westbound shoulder on WIS 153 will be closed from Old 51 to Water Street in Mosinee.
- Flagging operations will be utilized when materials and equipment are being delivered or removed. No delays are expected.
- Additionally, when pouring the concrete overlay July 15 traffic will be shifted. Westbound traffic will be shifted onto the westbound shoulder and eastbound traffic will be shifted into existing westbound lane.