Schedule and Traffic Impacts
Page last updated: Aug. 1, 2025
Schedule: June 16 to Sept. 9, 2025
Anticipated work scheduled: Crews will be working at both sites in the coming weeks. Crews will:
- Pittsville
- Start preparing the east cell of the box culvert for concrete overlay. Work includes removing all unsound materials, cleaning surfaces, and installing reinforcement.
Traffic impacts (the next 10 days):
- Pittsville
- The eastbound shoulder from WIS 80 to 4th Avenue and the westbound right turn lane for County A north will be closed. Flagging operations will be utilized when materials and equipment are being delivered or removed. No delays are expected.