I-94 North-South Freeway Project

Ryan Road Interchange

Project Updates

>>December 2017 Project Update

  • Lane closures along Ryan Road
    • Eastbound closures began December 7
    • Westbound closures began December 8
  • Overnight full freeway closure for bridge demolition
    • December 14 and 18
    • Ryan Road to remain open during demolition operations

>>Fall 2017 Project Update

Estimated Schedule

Fall 2017 to fall 2018

Traffic Impacts

  • Ryan Road Park and Ride closed December 3rd. View closure announcement here.
  • Single lanes along Ryan Road will be open heading eastbound and westbound across the bridge
  • Ramps to remain open throughout the project (except for minor short term closure to match new roadway configuration)
  • Minimal impacts to I-94 mainline

Contact Us

Brad Peterson, WisDOT Construction Project Leader

Ken Kiepczynski, PE., WisDOT Construction Project Manager