Schedule and Traffic Impacts
Page last updated: Sept. 4, 2026
Schedule: Aug. 24, 2026 to Aug. 17, 2027
Anticipated work scheduled: Crews will:
- Continue asphalt patching
- Remove concrete approaches, install storm sewer and continue grading.
- Pour concrete approaches
- Complete any restoration
- Begin sawing concrete
Traffic impacts (the next 10 days):
- All active lane closures on I-39 southbound will be removed by noon Friday Sept. 4 for the holiday weekend.
- Beginning Tuesday, Sept. 8 until mid-November there will be single lane closures on both I-39 southbound and I-39 northbound between Fawn Court and the Waushara County line.