I-39/90 Expansion Project

Illinois state line to Madison, Dane and Rock counties

Schedule

Note: Dates are subject to change.

Current/FutureI-39/90 shields

2018

 

2018-2021

  • Construction schedule for I-39/90 Expansion Project.
    Note: Dates are subject to change.

    • North Segment – Edgerton to Madison
      Dane/Rock County line to US 12/18 (Beltline) interchange
    • Central Segment – Janesville to Edgerton
      County O, south of Janesville, north to Dane/Rock County line
    • South Segment – Beloit to Janesville
      Illinois state line to County O, south of Janesville

Past

2018

2017

  • December 6, 2017 –Business meeting for US 14/Humes Road reconstruction, between WIS 26/Milton Avenue and Deerfield Drive in Janesville.
  • April – December 2017 – I-39/90 and County N interchange reconstruction, north of Stoughton.
  • June – November 2017 – Temporary widening on I-39/90 southbound from Madison to Edgerton, Dane County.
  • March – November 2017 – I-39/90 northbound expansion, from Dane/Rock County line to East Church Road.
  • Oct. 11 and 12, 2017 – Open house meetings for I-39/90 and County N interchange project.
  • April – Sept. 2017 – Manogue Road bridge replacement over I-39/90, north of Janesville.
  • March – Sept. 2017 – Temporary widening on I-39/90 southbound, Stateline Road bridge replacement, near Beloit.
  • March – August 2017 – County AB bridge replacement over I-39/90, Dane County.
  • August 22, 2017 – Public meeting for I-39/90 expansion, between Beloit and Janesville
  • May 18, 2017 – Central segment open house meeting, Janesville to Edgerton.
  • April 18, 2017 – Public meeting for I-39/90 and County N interchange
  • April 3, 2017 – North segment open house meeting, Edgerton to Madison
  • March 30, 2017 – South segment open house meeting, Beloit to Janesville

2016

 

2015

  • December 8, 2015 – Janesville Business Meeting (Central segment).
  • I-39/90 Project, 2015 construction activities.
    • Sept. 2015 – I-39/90 and WIS 11 (Avalon Road) interchange reconstruction began.
    • Aug./Sept. – Dec. 2015 – Two bridge replacement projects over I-39/90, north of Edgerton.
    • June – Nov. 2015 – WIS 73 and US 12/18 intersection construction, near Cambridge and Deerfield.
    • May – Dec. 2015 – County G (Prairie Avenue) reconstruction, north of Beloit.
    • April – Nov. 2015 – Reconfiguration of the I-39/90 and County S (Shopiere Road) interchange, north of Beloit.
    • April – Nov. 2015 – US 14 and US 51 alternate route improvements, Janesville to Edgerton.
    • April – Nov. 2015 – I-39/90 and WIS 73/US 51 interchange reconstruction.
  • March 25, 2015 – South segment open house meeting (Beloit to Janesville).
  • March 19, 2015 – Janesville Business Meeting (Central segment).
  • March 5, 2015 – North segment open house meeting (Edgerton to Madison).
  • March 4, 2015 – Central segment open house meeting (Janesville to Edgerton).
  • Feb. 11, 2015 – Public hearing for I-39/90 and I-43 interchange near Beloit.

2010-2014