Project Details
This project will make improvement to approximately seven (7) miles of I-94 between WIS 83 and WIS 16 in Waukesha County. Improvements will also be made to the the Meadowbrook and Nagawaukee park and rides as part of this project.
Improvements Include:
- Resurfacing of I-94 within project limits.
 - Deck sealing/preservation on four (4) bridges
- Maple Avenue, County SS, County T, and County JJ bridges
 
 - Resurfacing Meadowbrook and Nagawaukee park and rides.
 - Resurfacing on WIS 318, from Rolling Ridge Drive to I-94.
 - Base patching
 - Culvert repair
 - Retaining wall replacement
 - Signal improvements at County SS, County T, and WIS 318/Silvernail Road intersections
 
Traffic Impacts:
Work on I-94 will happen during overnight, non-peak travel hours.
- The speed limit will be reduced to 55 mph while overnight work is taking place
 - Overnight full freeway closures, single lane closures, local road closures, ramp closures
 - Partial closures of Meadowbrook and Nagawaukee park and rides.
- Limited access will be maintained during park and ride construction
 - Nagawaukee park and ride construction: summer 2024
 - Meadowbrook park and ride construction: late fall 2024
 
 
Schedule:
This project is scheduled to begin in late May 2024 and be completed by mid-2025.