Project Details
Location
The west side of I-41/I-894 between Cold Spring Road and Howard Avenue in the City of Greenfield, Milwaukee County.
2024 Project Improvements
Crews will be reconstructing the noise wall on the I-894 bridge over Cold Spring Road.
Schedule
2024 construction is anticipated to begin in late May and be complete by mid-summer 2024. All work is weather dependent and subject to change.
Traffic Impacts
- I-894 southbound traffic from Howard Avenue to 92nd Street will be shifted to the inside shoulder.
- ​Four (4) lanes will remain open on I-894 during peak travel hours. Overnight closures are anticipated.
- Cold Spring Road under I-894 is scheduled to close for about two (2) months while crews reconstruct the noise wall on the bridge.
- Motorists are encouraged to use WIS 1oo (108th Street), Layton Avenue, and 92nd Street to get around the closure.