The anticipated WisDOT schedule is:

  • Start: Week of May 3, 2021
    • However, construction on the city of Amery’s portion of the project begins Monday, March 29.
  • June:
    • Removal of existing asphalt and paving new asphalt on WIS 46 both the south and north ends of the city outside Amery’s project.
  • July:
    • Installation of new traffic signals at the WIS 46 intersections at Broadway Street East (County F) and Birch Street.
  • September:
    • Completing the project with final paving and pavement marking.