I-43 Resurfacing (WIS 60 to WIS 32)

Ozaukee County

Project Details

This project will resurface approximately 1.5 miles of I-43 between WIS 60 and WIS 32 in Ozaukee County. The park and ride at I-43 and County V (WIS 32) will also be resurfaced as part of this project.

Improvement Include:

  • Resurfacing of I-43 within project limits, including service ramps
  • Base patching
  • Cable guard installation and grading in median
  • Box culvert repairs
  • Repaving and new lighting at County V (WIS 32) Park and Ride.

Traffic Impacts:

Traffic will be maintained in both directions of I-43 during peak travel hours. Construction will be completed in multiple stages.

Stage 1 (Mid-June to Mid-July):

Cable barrier and beam guard improvements throughout project limits

  • Single lane and shoulder closures

Stage 2 (Mid-July to fall 2024):

  • Mill and overlay I-43 and service ramps within project limits
    • Overnight full freeway closures and ramp closures
    • Daytime single lane and shoulder closures
  • County V (WIS 32) Park and Ride improvements
    • One week closure, tentatively scheduled in October, for resurfacing and lighting improvements

Schedule:

Construction is scheduled to begin in mid-June and be complete in fall 2024.