Project Details
This project will make various improvements to approximately 2.6 miles of WIS 32 (N. Lake Drive) between E. Dean Road and E. School Road in the village of Fox Point, Milwaukee County.
Improvements Include:
- Rehabilitate roadway within project limits
- Watermain replacement
- Upgrade storm sewer and drainage equipment
- Crosswalk improvements
Traffic Impacts:
WIS 32 (N. Lake Drive) will be closed to through traffic during construction within the project limits. Local access will be maintained.
Residents are encouraged to use the nearest cross street to their destination when accessing WIS 32 (N. Lake Drive).
Detour:
A detour will be posted utilizing E. Silver Spring Drive and N. Port Washington Road.
Schedule:
This project is scheduled to begin in mid-March and be completed by late summer 2025. All work is weather dependent and subject to change.