Project Updates
May 23 Update
WIS 241 Upcoming Project Schedule Overview
This Week (through 5/23):
- Traffic Control
- Replace Curb and Gutter, Sidewalk, Ramps, Driveways
- Replaced Storm and Sanitary Manholes, Inlets, and Water Valves
- Switched over to new traffic signals equipment at Ramsey, Parnell, Grange, and Edgerton Ave intersections on the east side of 27th St.
Next Week (Week of 5/27):
- Daily Middle Lane Closures 6am – 2pm (NB)
- Daily Middle Lane Closure 6am – 2pm (SB)
- Continue sidewalk and concrete curb and gutter replacement work, including removal and excavation of old sidewalk and curb (SB)
- Continue placing concrete for new curb and gutter, sidewalk (NB)
- Continue Storm Sewer Repair and Replacement Work (SB)
- Asphalt Patching
Long Term (2+weeks / June)
- Complete NB 27th Street, and then move to SB 27th Street curbs and sidewalks.
- Long-Term 20-Day middle lane closure beginning on June 9th.
- Begin Milling of Lane 3 asphalt
- Begin base patching after milling
- Begin work at the Layton Ave intersection beginning after the July 4th Holiday.