Project Updates
April 11 Update
WIS 241 Project Schedule Overview
This Week:
- Traffic control
- Pavement sawing
- Removing and replace curb and gutter, sidewalk
- Traffic signals prep work
Next Week:
- Continue sidewalk and concrete curb and gutter replacement work, including removal and excavation of old sidewalk and curb
- Begin placing concrete for new curb and gutter, sidewalk
- Daily lane closures (northbound)
- Begin traffic signals electrical work
- Begin storm sewer repair and replacement work
Long Term (2+weeks)
- Complete northbound 27th Street, and then move to southbound 27th Street curbs and sidewalks.