WIS 241 Resurfacing (Layton Avenue to College Avenue)

Milwaukee County

Project Updates

April 11 Update

WIS 241 Project Schedule Overview

This Week:

  1. Traffic control
  2. Pavement sawing
  3. Removing and replace curb and gutter, sidewalk
  4. Traffic signals prep work

Next Week:

  1. Continue sidewalk and concrete curb and gutter replacement work, including removal and excavation of old sidewalk and curb
  2. Begin placing concrete for new curb and gutter, sidewalk
  3. Daily lane closures (northbound)
  4. Begin traffic signals electrical work
  5. Begin storm sewer repair and replacement work

Long Term (2+weeks)

  1. Complete northbound 27th Street, and then move to southbound 27th Street curbs and sidewalks.