September 17, 2024 update:
Westbound US 18/WIS 59 (Waukesha Bypass) traffic shift scheduled for Monday, September 23.
- Traffic will shift from the outside lane to the inside lane over the Fox River bridge.
- New traffic pattern will allow crews will begin bridge work on the outside lane
- Left turn movements will continue to be restricted to/from Fox River Parkway
- Right turns will be accessible to/from Fox River Parkway
- Traffic will continue to be maintained in both directions within work zone
Construction is scheduled for completion in late 2024.