US 18/WIS 59 (Waukesha Bypass) Bridge Rehabilitation

Waukesha County

Project Details

This project will make improvements to the eastbound US 18/WIS 59 (Waukesha Bypass) bridge over the Fox River in Waukesha County.

Project Details:

  • The eastbound US 18/WIS 59 bridge will be re-decked.
  • Installation of two new concrete girders.
  • Wingwall abutment repairs on north side of bridge.
  • New pavement approaches on both sides of bridge.

Traffic Impacts:

Traffic will be maintained in both directions of US 18/WIS 59 over the Fox River. Access to local residents and businesses will also be maintained.

Single lane closures for bridge re-decking work:

  • Stage 1: Lane one (inside lane) will be closed for approximately 65 days starting in early July.
    • Left turn access onto Fox River Parkway from eastbound US 18/WIS 59 will be closed during stage one.
    • Left turns from southbound Fox River Parkway to US 18/WIS 59 will be restricted during stage one.
  • Stage 2: Lane two (outside lane) will be closed for approximately 65 days after lane one is completed.

Schedule:

Work is tentatively scheduled to begin in early July 2024 and be complete by late 2024.