Project Details
This project will make improvements to the eastbound US 18/WIS 59 (Waukesha Bypass) bridge over the Fox River in Waukesha County.
Project Details:
- The eastbound US 18/WIS 59 bridge will be re-decked.
- Installation of two new concrete girders.
- Wingwall abutment repairs on north side of bridge.
- New pavement approaches on both sides of bridge.
Traffic Impacts:
Traffic will be maintained in both directions of US 18/WIS 59 over the Fox River. Access to local residents and businesses will also be maintained.
Single lane closures for bridge re-decking work:
- Stage 1: Lane one (inside lane) will be closed for approximately 65 days starting in early July.
- Left turn access onto Fox River Parkway from eastbound US 18/WIS 59 will be closed during stage one.
- Left turns from southbound Fox River Parkway to US 18/WIS 59 will be restricted during stage one.
- Stage 2: Lane two (outside lane) will be closed for approximately 65 days after lane one is completed.
Schedule:
Work is tentatively scheduled to begin in early July 2024 and be complete by late 2024.