WIS 175 Intersections

Waukesha County

Project Overview

Location

WIS 175 (Appleton Avenue) intersections with Menomonee Avenue and Pilgrim Road in Menomonee Falls. More info HERE.

Proposed improvements

  • Grading
  • Curb and gutter
  • Asphalt pavement
  • Traffic signals and lighting
  • Pedestrian access
  • Pavement markings

Traffic impacts

Through access will be maintained during the course of the project, however staging will require lane closures on WIS 175 (Appleton Ave.).

Schedule

  • Work is scheduled to begin the week of June 8
  • Early September – Complete construction of all curb, pavement, signing, marking – remove all traffic restrictions
  • Spring 2021 – Remove temporary signal control, complete installation of new signal equipment

All work schedules are subject to change.