Project Overview
Location
WIS 175 (Appleton Avenue) intersections with Menomonee Avenue and Pilgrim Road in Menomonee Falls. More info HERE.
Proposed improvements
- Grading
- Curb and gutter
- Asphalt pavement
- Traffic signals and lighting
- Pedestrian access
- Pavement markings
Traffic impacts
Through access will be maintained during the course of the project, however staging will require lane closures on WIS 175 (Appleton Ave.).
Schedule
- Work is scheduled to begin the week of June 8
- Early September – Complete construction of all curb, pavement, signing, marking – remove all traffic restrictions
- Spring 2021 – Remove temporary signal control, complete installation of new signal equipment
All work schedules are subject to change.