Project Updates
May 19 Update:
Traffic:
1) The WIS 164 full roadway closure remains unchanged. No other closures planned.
2) Access to residence and business will be maintained, please follow the detour.
Contractor Operations this week:
1) Continue HMA (hot mix asphalt) paving, mainline surface layer Monday and Tuesday, May 19 – 20, 2025
2) Continue HMA (hot mix asphalt) paving, intersections and turn lanes surface layer Wednesday and Thursday, May 21 – 22, 2025
Looking Ahead:
1) Shouldering, guardrail, sign and restoration the week of 05/26/2025.