WIS 164 Resurfacing (Henneberry Avenue to Denoon Road)

Waukesha County

Project Updates

July 14 Update:

The roadway is still closed, and the contractor will be onsite this week to finish restoration, install permanent signing and punch list items.

Please see below for an update about the work occurring this week.

Traffic:

1)       The WIS 164 full roadway closure remains unchanged. No other closures planned.

2)       Access to residence and business will be maintained, please follow the detour

Contractor Operations this week:

1)       Restoration and Permanent Signing

2)       Punchlist items.

3)       Finishing roadway items and opening by Friday July 18, 2025.

Looking Ahead:

1)       Addressing comments after the project walk through and any remaining punch list items.