Project Details
This pavement resurfacing project will make improvements to segments of the I-43 Rock Freeway between US 12 and WIS 83 in Walworth and Waukesha Counties.
Project Improvements:
- Remove 2.5 inches of asphalt pavement in sections of I-43 and replace it with new asphalt pavement.
- Update signing and pavement markings
Traffic Impacts:
There will be no detour needed for this project. Traffic will be maintained in both directions of I-43 during construction.
Work will be done in two stages:
- Stage 1A: I-43 northbound and southbound inside lanes will be closed
- Stage 1B: I-43 northbound and southbound outside lanes will be closed
Access to local businesses and residents will be maintained.
Schedule:
Work will begin in early May and is scheduled for completion in late summer 2024.