US 12 Resurfacing & WIS 11 Culvert Replacement

Walworth County

US 12 Weekly Updates

November 1, 2024 Update

Current Construction Operations:

  • Bridge work complete.
  • Asphalt paving near the bridge wrapped up earlier this week, crews are currently working on aggregate shoulders, guardrail, pavement markings and other finishing items in this area.
  • Aggregate shoulder work south of County A started yesterday and will continue into next week.
  • Pavement marking work continues and will be ongoing through the weekend into next week.

Upcoming Construction Operations (Week of 11/4/2024):

  • Pavement marking work will be ongoing and is anticipated to wrap up by mid-week.
  • Traffic signal work will resume mid-week with installation of large concrete bases at the County ES intersection. This work will require large equipment to utilize the roadway.
  • Aggregate shoulder placement is anticipated to wrap up early week.

Traffic Updates:

  • US 12 is closed to through traffic (residents and business will have access), a detour route utilizing WIS 20, I-43 and WIS 67 is in place.
  • No traffic will be allowed to cross the Sugar Creek Bridge for the duration of this project (Located between County A and County ES.)
  • The project is anticipated to wrap up by mid to late November.