June 28 Update:

Upcoming Construction Operations (Monday July 1st):

  • Erosion Control installations, guardrail removals, sign removals
  • Grubbing operations
  • Grading operations

Traffic Updates:

  • PCMS (message signs) will be placed on northbound and southbound WIS 36/83 at the intersection of WIS 11/County E.
  • Message signs activated Monday June 17th.
  • WIS 11/County J will close June 27th, 2024.
  • WIS 11/County J will remain closed for the duration of the project. A detour route utilizing WIS 75, WIS 142 and WIS 83/36/11 will be posted
  • The project is anticipated to wrap up by mid-September.

Resident and Business Access:

  • The Residents at #3504 S. English Settlement Ave and the Venture Inn Bar & Grill will always have access unless the contractor is working in front of their driveways for the duration of the work.

All work is weather dependent and subject to change.