Project Updates
June 28 Update:
Upcoming Construction Operations (Monday July 1st):
- Erosion Control installations, guardrail removals, sign removals
- Grubbing operations
- Grading operations
Traffic Updates:
- PCMS (message signs) will be placed on northbound and southbound WIS 36/83 at the intersection of WIS 11/County E.
- Message signs activated Monday June 17th.
- WIS 11/County J will close June 27th, 2024.
- WIS 11/County J will remain closed for the duration of the project. A detour route utilizing WIS 75, WIS 142 and WIS 83/36/11 will be posted
- The project is anticipated to wrap up by mid-September.
Resident and Business Access:
- The Residents at #3504 S. English Settlement Ave and the Venture Inn Bar & Grill will always have access unless the contractor is working in front of their driveways for the duration of the work.
All work is weather dependent and subject to change.