Latest News
Nov. 25, 2026
The Wisconsin Department of Transportation (WisDOT) provides weekly updates on road construction projects in the following counties in northwest Wisconsin: Ashland, Barron, Bayfield, Buffalo, Burnett, Chippewa, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, Rusk, St. Croix, Sawyer, Taylor, Trempealeau and Washburn counties.
Bayfield County
Highway: WIS 13
Location: Lake Superior Wayside between Iron River and Port Wing about 0.48 mile west of Airport Road
Schedule: July 13 to late November
Cost: $3.98 million
Description of work: On the shoreline from the west property line to Jardine Creek: Armoring the toe of the slope using a 6-inch-thick layer of bedding stone, a 3-foot-thick layer of underlying stone and a 6-foot-thick layer of armor stone; excavating a 4:1 slope from the newly constructed armored to the top of the existing slope; and stabilizing the excavated slope with turf reinforcement mat and garden with topsoil and seed. At the wayside: Milling 2 inches of existing asphalt and paving 2 inches of new asphalt in the parking lot and WIS 13 entrance; upgrading the walking path to meet Americans With Disabilities Act standards by grading base aggregate and overlaying with 2 inches of new asphalt; replacing the culvert and apron end walls below the walking path to the lake and at the WIS 13 entrance to the wayside; replacing the timber guard posts bordering the parking area; and repairing the crack in the concrete slab under the pavilion
Traffic impacts: WIS 13 remains open to traffic, but the wayside is closed for the duration of work.
***
Clark County
Highway: Pine Road
Location: South Fork Eau Claire River Bridge east of Thorp
Schedule: Oct. 5 to mid-November
Cost: $432,951
Description of work: Replacing the bridge and reconstructing the roadway approaching the bridge
Traffic Impacts: None; project complete.
***
Highway: Riplinger Road
Location: Nelson Creek Bridge northeast of Greenwood
Schedule: Oct. 12 to early December
Cost: $411,374
Description of work: Replacing the bridge
Traffic Impacts: Motorists are using a temporary bypass to get around the construction site.
***
Douglas County
Highway: South Mail Road
Location: St. Croix River Bridge west of Gordon
Schedule: Sept. 21 to late November, 2026 construction; work will resume in spring 2027
Cost: $969,042
Description of work: Replacing the bridge and reconstructing approach pavement
Traffic Impacts: South Mail Road is closed between Hill Road and Crotte Brook Road.
***
Highway: Winter Street and Susquehanna Avenue
Location: Winter Street, US 53 to Susquehanna Avenue, and Susquehanna Avenue, Winter Street to US 2 (Belknap Street), all in the city of Superior
Schedule: Sept. 15 to mid-November
Cost: This project is part of the $1.8-billion Blatnik Bridge replacement project, a joint Wisconsin and Minnesota Departments of Transportation project that began in September 2026 and is scheduled for completion in mid-2032.
Description of work: Removing a portion of existing pavement on Winter Street and Susquehanna Avenue and placing a new layer of asphalt over the roadways; adding a left-turn lane for northbound traffic on Susquehanna Avenue at the on-ramp to westbound US 2; adding pavement markings to delineate additional turn lanes, as room allows, on the corridor; adding temporary traffic signals on Winter Street at Grand Avenue; adding stop signs on Winter Street at Catlin Avenue and adjusting other stop signs at intersections along Winter Street; making pavement marking modifications along Belknap Street; and removing left-turn lanes along Belknap at Banks and Ogden avenues
Traffic Impacts: Winter Street remains open to traffic, but motorists might encounter lane closures as finishing work is completed.
***
Highway: WIS 13
Location: Bridge over US 2/53 southeast of Superior
Schedule: June 8 to late November
Cost: $1.43 million
Description of work: Replacing bridge joints, making surface repairs to abutments, cleaning and painting bridge girders and bearings, replacing concrete approach slabs at each end of bridge, replacing asphalt roadway approaches for about 100 feet and replacing the guardrail bridge connections
Traffic Impacts: None.
***
Highway: WIS 27
Location: Sandy Run Creek south of US 2
Schedule: Aug. 3 to late November
Cost: $1.66 million
Description of work: Removing the existing culvert, replacing it with a single-span concrete girder bridge, replacing approach pavement and guardrail and placing new pavement markings
Traffic Impacts: WIS 27 is closed from the project’s northern terminus to about four-tenths of a mile south of US 2.
- Traffic is being detoured via Bayfield County N, County A and US 2.
***
Highway: WIS 105
Location: Unnamed tributary of the Pokegama River in Superior
Schedule: June 15 to mid-November, 2026 construction; work to resume in 2027
Cost: $3.06 million
Description of work: Removing the existing culvert, building a temporary bypass to carry a single lane of traffic during construction, constructing a bridge to replace the culvert, replacing pavement approaching the new structure, installing guardrail, removing the temporary bypass and repairing slopes disturbed by construction
Traffic Impacts: WIS 105 and the new bridge are open to traffic, completing work for 2026.
***
Dunn County
Highway: WIS 170
Location: Red Cedar River Bridge in Colfax
Schedule: Aug. 17 to late November
Cost: $1.88 million
Description of work: Replacing the bridge deck, one of the existing steel beams and concrete bridge approaches
Traffic Impacts: WIS 170 is reduced to a single lane of traffic controlled by temporary traffic signals.
***
Eau Claire County
Highway: I-94
Location: US 53 interchange to Mallard Road southwest of Eau Claire
Schedule: March 23 to late November, 2026 construction; and March 4, 2024, to spring 2027, overall project
Cost: $69.9 million
Description of 2026 work: Replacing the pavement on eastbound I-94 from Otter Creek to Mallard Road, the eastbound bridges over County J and County D and the box culvert carrying Kluckman Valley Creek under eastbound I-94 near County D; completing shoulders, removing temporary lanes and structures and restoring the interstate’s median
Traffic Impacts: None; project complete for 2026.
***
Pepin County
Highway: US 10
Location: WIS 25 North intersection west of Durand
Schedule: July 7 to mid-November
Cost: $2.62 million
Description of work: Constructing a single-lane roundabout at the intersection, installing curb and gutter, replacing culverts and storm sewer and installing lighting
Traffic Impacts: None; project complete.
***
Polk County
Highway: WIS 87
Location: US 8 to 240 feet north of Minnesota Street in St. Croix Falls
Schedule: April 24 to mid-November
Cost: $1.7 million
Description of work: Removing 3.25 inches of existing pavement and paving 3.25 inches of hot-mix asphalt, replacing curb ramps, removing roadway pavers, adjusting manhole covers, inlet covers and water valves, installing storm sewer and placing new pavement markings
Traffic impacts: WIS 87 is open to traffic, but motorists will encounter parking lane closures as crews return the week of Nov. 30 to complete pavement markings.
***
Highway: WIS 243
Location: St. Croix River Bridge between WIS 35 in Osceola and MN 95 in Franconia Township, MN
Schedule: Aug. 10, 2026, to fall 2028
Cost: $23.2 million; this is a joint project of the Wisconsin and Minnesota Departments of Transportation.
Description of work: Replacing the bridge on its existing alignment and building a new pedestrian and bicycle path
Traffic impacts: WIS 243 and the bridge are closed.
- Traffic is being detoured via WIS 35, US 8 and MN 95.
- Motorists also can use the alternative route of WIS 35, WIS 35/64, WIS 64, MN 36 and MN 95.