Zoo Interchange Project

Latest Traffic Report: 4/25/17

List of all scheduled closures and restrictions on the Zoo Interchange Project from April 25 – April 30:

Tuesday (4/25)

Zoo Interchange Project

– a lane will be closed 4/6 through 5/8 on the Bluemound Rd entrance ramp to I-41 for barrier wall work.

 

Wednesday (4/26)

Zoo Interchange Project

– a lane will be closed 4/6 through 5/8 on the Bluemound Rd entrance ramp to I-41 for barrier wall work.

– there will be a full closure overnight I-41/894 NB at Greenfield Ave for equipment mobilization.   *contingency is Thursday 4/27

– there will be a full closure overnight I-41 SB at the Zoo Interchange for equipment mobilization.   *contingency is Thursday 4/27

– a lane will be closed overnight I-41 NB from the Zoo Interchange to Bluemound Rd for asphalt work.

– the Zoo Int E-N system ramp will be closed overnight for asphalt work.

 

Thursday (4/27)

Zoo Interchange Project

– a lane will be closed 4/6 through 5/8 on the Bluemound Rd entrance ramp to I-41 for barrier wall work.

 

Friday (4/28)

Zoo Interchange Project

– a lane will be closed 4/6 through 5/8 on the Bluemound Rd entrance ramp to I-41 for barrier wall work.

– there will be a full closure overnight I-94 EB at Moorland Rd for sign structure work.

– there will be a full closure overnight I-94 WB at the Zoo Interchange for sign structure work.

– the Zoo Int N-W system ramp will be closed overnight for sign structure work.

– the Zoo Int S-W system ramp will be closed overnight for sign structure work.

 

Saturday (4/29)

Zoo Interchange Project

– a lane will be closed 4/6 through 5/8 on the Bluemound Rd entrance ramp to I-41 for barrier wall work.

 

STH 164 Project

– a lane will be closed during the day STH 164 NB/SB at I-43 for basepatching and detector work.

 

Sunday (4/30)

Zoo Interchange Project

– a lane will be closed 4/6 through 5/8 on the Bluemound Rd entrance ramp to I-41 for barrier wall work.

– a lane will be closed overnight I-41/894 SB north of Coldspring Rd for soil boring.

 

Long-Term Closures

Zoo Interchange Project

– there will be a full closure of the HWY 100 entrance ramp to I-94 EB through 5/7 for roadway reconstruction.

– there will be a full closure of the Zoo Int W-N system ramp through late May 2017 for ramp reconstruction.

– there will be a full closure of the Zoo Int N-E system ramp through late May 2017 for ramp reconstruction.

– there will be a full closure of Wisconsin Ave EB/WB from 95th St to 97th St through late May 2017 for reconstruction.

– there will be a full closure of the Bluemound Rd entrance ramp to I-41 SB through late August 2017 for ramp reconstruction.

– there will be a full closure Elm Grove Rd NB/SB at I-94 through late August 2017 for bridge reconstruction.

– there will be a full closure of Fairview Ave WB from 116th St to Curtis Rd through late Summer 2017 for retaining wall construction (local access maintained).

– there will be a full closure of Fairview Ave EB from 118th St to 116th St through late Summer 2017 for retaining wall construction (becomes one-way WB only).

– there will be a full closure of the Lincoln Ave entrance ramp to I-41/894 NB through early Fall 2017 for roadway construction.

– there will be a full closure of the Greenfield Avenue entrance ramp to I-41/894 SB through early Fall 2017 for roadway construction.

– a lane will be closed on Curtis Rd NB/SB under I-94 through Fall 2017 for roadway construction.

– there will be a full closure of the HWY 100 entrance ramp to I-94 WB through Fall 2017 for ramp reconstruction.

– there will be a full closure from 100th St NB/SB from Orchard St to Maple St 3/27 through Fall 2017 for roadway work.

– there will be a full closure of the I-94 WB exit ramp to HWY 100 NB through late November 2017 for roadway reconstruction.

– there will be a full closure of the I-94 WB exit ramp to HWY 100 SB (from I-94 WB and I-41/894 NB) through late November 2017 for roadway reconstruction.

– there will be a full closure of the Zoo Int E-S system ramp through late November 2017 for ramp reconstruction.

– there will be a full closure of the I-94 EB exit ramp to 84th St (from I-94 EB and I-41 SB) through late November 2017 for roadway reconstruction.

– there will be a full closure of the Greenfield Ave entrance ramp to I-41/894 NB (to I-41 NB and I-94 WB) through late 2017 for ramp reconstruction.

– there will be a full closure of the Deer Creek Trail/Oak Leaf Trail NB/SB at I-94 through late 2017 for bridge demolition (one trail will remain open at all times).

– there will be a full closure of the I-41 NB exit ramp to Bluemound Rd through late April 2018 for ramp reconstruction.

– there will be a full closure of the I-41/894 SB exit ramp to Greenfield Ave through early Summer 2018 for roadway construction.

– there will be a full closure of the I-41/894 SB exit ramp to Lincoln Ave through early Summer 2018 for roadway construction.

– there will be a full closure of Schlinger Ave EB/WB under I-41/894 through early Summer 2018 for project construction.

– the Hank Aaron State Trail will be closed to pedestrians from 94th Pl to Oak Leaf Trail through early Summer 2018 for project construction.