List of all scheduled closures and restrictions on the Zoo Interchange Project from June 28 – July 9:

Wednesday (6/28)

Zoo Interchange Project

– there will be a full closure overnight I-41/894 NB at Greenfield Ave for overhang work.

– there will be a full closure overnight I-41 SB at Bluemound Rd for overhang work.

– the Zoo Int W-N system ramp will be closed overnight for overhang work.

 

Waukesha Co Joint Repair Project

– lanes will be closed overnight I-94 WB from CTH G to Elmhurst Rd for joint repair.

 

Thursday (6/29)

Zoo Interchange Project

– a lane will be closed during the day HWY 100 SB from Rogers St to Becher St for Milwaukee Co Maintenance pavement repair.

– lanes will be closed during the day Greenfield Ave WB from 116th St to Rainbow Ave for City of West Allis pavement restoration.

– a lane will be closed during the day Burleigh St EB at 124th St for signal work.

– a lane will be closed during the day Hampton Ave EB/WB at I-41 for signal work.

– a lane will be closed during the day North Ave WB at 124th St for signal work.

– a lane will be closed during the day 124th St NB at North Ave for signal work.

– a lane will be closed during the day 124th St NB at Burleigh St for signal work.

– a lane will be closed overnight I-41/894 SB from Howard Ave to Coldspring Rd for soil boring.

– there will be a full closure overnight I-41/894 NB at Greenfield Ave for overhang work.   *contingency is Friday 6/30

– there will be a full closure overnight I-41 SB at Bluemound Rd for overhang work.   *contingency is Friday 6/30

– the Zoo Int W-N system ramp will be closed overnight for overhang work.   *contingency is Friday 6/30

 

Waukesha Co Joint Repair Project

– lanes will be closed overnight I-94 WB from Elmhurst Rd to CTH C for joint repair.

 

Nor-X-Way Channel Project

– lanes will be closed overnight I-41 SB at Pilgrim Rd for a traffic switch.   *contingency is Wednesday 7/5

 

Friday (6/30)

Zoo Interchange Project

– lanes will be closed during the day Greenfield Ave WB from 116th St to Rainbow Ave for City of West Allis pavement restoration.

– a lane will be closed during the day Hampton Ave EB/WB at I-41 for signal work.

 

Saturday (7/1)

Zoo Interchange Project

– only long-term closures in effect.

 

Sunday (7/2)

Zoo Interchange Project

– there will be a full closure 1pm through 8pm Greenfield Ave EB/WB from 68th St to 84th St for the City of West Allis Fourth of July parade.

 

Monday (7/3)

Zoo Interchange Project

– only long-term closures in effect.

 

Tuesday (7/4)

Zoo Interchange Project

– only long-term closures in effect.

 

Wednesday (7/5)

Zoo Interchange Project

– a lane will be closed long-term 6am through mid/late July 2017 84th St SB at Bluemound Rd for roadway work.

– a right-turn lane will be closed long-term 6am through early August 2017 Bluemound Rd EB at 84th St for roadway work.

– there will be a full closure long-term 6am through late August 2017 of the I-41 NB exit ramp to Capitol Dr for intersection reconstruction.

– there will be a full closure long-term 6am through late August 2017 of the Capitol Dr EB/WB frontage road at I-41 for intersection reconstruction (EB/WB access on Capitol Dr is maintained on the lower roadway).

– a lane will be closed long-term 6am through mid-November 2017 Watertown Plank Rd EB/WB from HWY 100 to 115th St for bridge reconstruction.

– a left-turn lane will be closed long-term 6am through mid-November 2017 HWY 100 NB at Watertown Plank Rd for bridge reconstruction.

– a lane will be closed during the day Burleigh St EB at 124th St for signal work.

– a lane will be closed during the day North Ave WB at 124th St for signal work.

– a lane will be closed during the day 124th St NB at North Ave for signal work.

– a lane will be closed during the day 124th St NB at Burleigh St for signal work.

– there will be a full closure overnight I-41/894 NB at Greenfield Ave for overhang work.   *contingency is Friday 7/7

– there will be a full closure overnight I-41 SB at Bluemound Rd for overhang work.   *contingency is Friday 7/7

– the Zoo Int W-N system ramp will be closed overnight for overhang work.   *contingency is Friday 7/7

 

Waukesha Co Joint Repair Project

– lanes will be closed overnight I-94 WB from Elmhurst Rd to CTH C for joint repair.

 

Thursday (7/6)

Zoo Interchange Project

– a lane will be closed during the day Burleigh St EB at 124th St for signal work.

– a lane will be closed during the day 124th St NB at Burleigh St for signal work.

– there will be a full closure overnight I-41/894 NB at Greenfield Ave for overhang work.   *contingency is Friday 7/7

– there will be a full closure overnight I-41 SB at Bluemound Rd for overhang work.   *contingency is Friday 7/7

– the Zoo Int W-N system ramp will be closed overnight for overhang work.   *contingency is Friday 7/7

 

Waukesha Co Joint Repair Project

– lanes will be closed overnight I-94 WB from CTH C to STH 83 for joint repair.

 

Friday (7/7)

Zoo Interchange Project

– a lane will be closed during the day Burleigh St EB at 124th St for signal work.

– a lane will be closed during the day North Ave WB at 124th St for signal work.

– a lane will be closed during the day 124th St NB at North Ave for signal work.

– a lane will be closed during the day 124th St NB at Burleigh St for signal work.

– lanes will be closed overnight I-41/894 NB from Beloit Rd to National Ave for pavement marking.

– there will be a full closure overnight I-94 EB at HWY 100 for pier work.

– there will be a full closure overnight I-94 WB at the Zoo Interchange for overhang work.

– the Zoo Int N-E system ramp will be closed overnight for decking.

– the Zoo Int N-W system ramp will be closed overnight for decking.

 

Waukesha Co Joint Repair Project

– lanes will be closed overnight I-94 WB from CTH C to STH 83 for joint repair.

 

Saturday (7/8)

Zoo Interchange Project

– only long-term closures in effect.

 

Sunday (7/9)

Zoo Interchange Project

– only long-term closures in effect.

 

Long-Term Closures

Zoo Interchange Project

– a lane will be closed on 124th St NB at Burleigh St through early July 2017 for signal work.

– a lane will be closed HWY 100 SB under I-41 through mid-July 2017 for AT&T utility work.

– a lane will be closed 84th St SB at Bluemound Rd 7/5 through mid/late July 2017 for roadway work.

– a right-turn lane will be closed Bluemound Rd EB at 84th St 7/5 through early August 2017 for roadway work.

– lanes will be closed North Ave WB under I-41 through late August 2017 for WE Energies utility work.

– there will be a full closure of the Bluemound Rd entrance ramp to I-41 SB through late August 2017 for ramp reconstruction.

– there will be a full closure Elm Grove Rd NB/SB at I-94 through late August 2017 for bridge reconstruction.

– there will be a full closure of the I-41 NB exit ramp to Capitol Dr 7/5 through late August 2017 for intersection reconstruction.

– there will be a full closure of the Capitol Dr EB/WB frontage road at I-41 7/5 through late August 2017 for intersection reconstruction (EB/WB access on Capitol Dr is maintained on the lower roadway).

– there will be a full closure of Fairview Ave WB from 116th St to Curtis Rd through late Summer 2017 for retaining wall construction (local access maintained).

– there will be a full closure of Fairview Ave EB from 118th St to 116th St through late Summer 2017 for retaining wall construction (becomes one-way WB only).

– there will be a full closure of the Lincoln Ave entrance ramp to I-41/894 NB through early Fall 2017 for roadway construction.

– there will be a full closure of the Greenfield Avenue entrance ramp to I-41/894 SB through early Fall 2017 for roadway construction.

– a lane will be closed on Curtis Rd NB/SB under I-94 through Fall 2017 for roadway construction.

– there will be a full closure of the HWY 100 entrance ramp to I-94 WB through Fall 2017 for ramp reconstruction.

– there will be a full closure of the I-94 WB exit ramp to HWY 100 through Fall 2017 for ramp reconstruction.

– there will be a full closure from 100th St NB/SB from Orchard St to Maple St through Fall 2017 for roadway work.

– there will be a full closure of 100th St NB from Madison Pl to Washington St through Fall 2017 for retaining wall construction (becomes one-way SB only).

– a lane will be closed Watertown Plank Rd EB/WB from HWY 100 to 115th St 7/5 through mid-November 2017 for bridge reconstruction.

– a left-turn lane will be closed HWY 100 NB at Watertown Plank Rd 7/5 through mid-November 2017 for bridge reconstruction.

– there will be a full closure of the Zoo Int E-S system ramp through late November 2017 for ramp reconstruction.

– there will be a full closure of the I-94 EB exit ramp to 84th St (from I-94 EB and I-41 SB) through late November 2017 for roadway reconstruction.

– there will be a full closure of the Greenfield Ave entrance ramp to I-41/894 NB (to I-41 NB and I-94 WB) through late 2017 for ramp reconstruction.

– there will be a full closure of the 84th St entrance ramp to I-94 WB (to I-94 WB) through late 2017 for roadway reconstruction.

– there will be a full closure of the Deer Creek Trail/Oak Leaf Trail NB/SB at I-94 through late 2017 for bridge demolition (one trail will remain open at all times).

– there will be a full closure of the I-41 NB exit ramp to Bluemound Rd through late April 2018 for ramp reconstruction.

– there will be a full closure of the I-41/894 SB exit ramp to Greenfield Ave through early Summer 2018 for roadway construction.

– there will be a full closure of the I-41/894 SB exit ramp to Lincoln Ave through early Summer 2018 for roadway construction.

– there will be a full closure of Schlinger Ave EB/WB under I-41/894 through late Summer 2018 for project construction.

– the Hank Aaron State Trail will be closed to pedestrians from 94th Pl to Oak Leaf Trail through late Summer 2018 for project construction.