Zoo Interchange Project

Latest Traffic Report: 8/15/18

List of all scheduled closures and restrictions on the Zoo Interchange Project from August 15 – August 26:

Wednesday (8/15)

Zoo Interchange Project

– a lane will be closed overnight National Ave EB/WB at I-41/894 for cable removal.

– lanes will be closed overnight I-43/894 WB from 76th St to 84th St for paving.

– lanes will be closed overnight I-94 EB from Moorland Rd to 124th St for mill and fill and staining.

– lanes will be closed overnight I-94 WB from Moorland Rd to 124th St for sawcutting.

– there will be a full closure overnight I-41/894 SB at National Ave for paving.

– there will be a full closure overnight I-94 WB at 84th St for downspout work.   *contingency is Thursday 8/16

– the Zoo Int N-W system ramp will be closed overnight for electrical work.   *contingency is Thursday 8/16

 

Thursday (8/16)

Zoo Interchange Project

– a lane will be closed during the day HWY 100 SB from National Ave to Oklahoma Ave for pavement restoration.

– a lane will be closed overnight I-94 WB at the Zoo Interchange for downspout work.

– lanes will be closed overnight I-94 EB from Moorland Rd to 124th St for mill and fill and staining.

– there will be a full closure overnight I-41/894 SB at National Ave for paving.   *contingency is Friday 8/17

– there will be a full closure overnight I-94 EB at the Zoo Interchange for signage work.   *contingency is Friday 8/17

– the Zoo Int N-E system ramp will be closed overnight for pavement marking.   *contingency is Friday 8/17

– the Zoo Int S-E system ramp will be closed overnight for pavement marking.

 

Friday (8/17)

Zoo Interchange Project

– a lane will be closed during the day HWY 100 SB from National Ave to Oklahoma Ave for pavement restoration.

– a lane will be closed during the day Lincoln Ave EB from 102nd St to I-41/894 for electrical work.

– a lane will be closed overnight HWY 100 SB at I-94 for a deck pour.   *contingency is Saturday 8/18

– a lane will be closed overnight I-41/894 NB from Howard Ave to National Ave for barrier wall removal.

– lanes will be closed overnight I-94 EB from Moorland Rd to 124th St for deck stripping.

– lanes will be closed overnight I-41/894 NB from Lincoln Ave to the Zoo Interchange for storm sewer crossing.

– a lane will be closed overnight I-43 NB from 116th St to the Hale Interchange for decking removal.

– there will be a full closure overnight I-41 SB at Watertown Plank Rd for pavement marking.

– there will be a full closure overnight I-94 WB at HWY 100 for storm sewer crossing.

– the Zoo Int N-W system ramp will be closed overnight for storm sewer crossing.

– the Zoo Int S-E system ramp will be closed overnight for storm sewer crossing.

– the Zoo Int S-W system ramp will be closed overnight for storm sewer crossing.

– the Zoo Int E-N system ramp will be closed overnight for pavement marking.

– the Zoo Int E-S system ramp will be closed overnight for pavement marking.

– the Zoo Int W-N system ramp will be closed overnight for pavement marking.

– the Zoo Int W-S system ramp will be closed overnight for pavement marking.

– the Hale Int W-N system ramp will be closed overnight for decking removal.

 

Saturday (8/18)

Zoo Interchange Project

– a lane will be closed in the morning I-41/894 SB from Greenfield Ave to Lincoln Ave for barrier wall work.

– a lane will be closed during the day I-41/894 NB from Greenfield Ave to the Zoo Interchange for barrier wall work.

– lanes will be closed overnight I-41/894 NB from Lincoln Ave to the Zoo Interchange for storm sewer crossing.

– a lane will be closed overnight I-41/894 NB from the Hale Interchange to National Ave for barrier wall removal.

– a lane will be closed overnight I-43/894 WB from 92nd St to the Hale Interchange for barrier wall removal.

– a lane will be closed overnight on the Hale Int E-N system ramp for barrier wall removal.

– there will be a full closure overnight I-41 SB at Bluemound Rd for pavement marking.

– there will be a full closure overnight I-41/894 SB at National Ave for pavement marking.    *contingency is Sunday 8/19

– there will be a full closure overnight I-94 WB at HWY 100 for storm sewer crossing.

– the Zoo Int N-W system ramp will be closed overnight for storm sewer crossing.

– the Zoo Int S-E system ramp will be closed overnight for storm sewer crossing.

– the Zoo Int S-W system ramp will be closed overnight for storm sewer crossing.

– the Zoo Int E-N system ramp will be closed overnight for barrier wall work.

– the Zoo Int E-S system ramp will be closed overnight for barrier wall work.

– the Zoo Int W-N system ramp will be closed overnight for barrier wall work.

– the Zoo Int W-S system ramp will be closed overnight for barrier wall work.

 

Sunday (8/19)

Zoo Interchange Project

– there will be a full closure overnight I-41/894 NB at National Ave for mill and fill.

– there will be a full closure overnight I-41 SB at Bluemound Rd for barrier wall work.

– the Zoo Int E-N system ramp will be closed overnight for barrier wall work.

– the Zoo Int E-S system ramp will be closed overnight for barrier wall work.

– the Zoo Int W-N system ramp will be closed overnight for barrier wall work.

– the Zoo Int W-S system ramp will be closed overnight for barrier wall work.

 

Monday (8/20)

Zoo Interchange Project

– the Beloit Rd entrance ramp to I-41/894 NB reopens to traffic by 5am.

– a lane will be closed overnight HWY 100 SB at I-94 for a deck pour.   *contingency is Tuesday 8/20

– lanes will be closed overnight I-43/894 EB from the Hale Interchange to 84th St for paving.

– lanes will be closed overnight I-94 EB from Moorland Rd to 124th St for mill and fill and staining.

– there will be a full closure overnight I-41/894 NB at National Ave for mill and fill.

– there will be a full closure overnight I-41/894 SB at National Ave for paving.

– the Zoo Int E-N system ramp will be closed overnight for barrier wall work.

– the Zoo Int W-N system ramp will be closed overnight for barrier wall work.

– the Hale Int W-E system ramp will be closed overnight for paving.

 

Tuesday (8/21)

Zoo Interchange Project

– lanes will be closed overnight I-43/894 WB from 76th St to 84th St for paving.

– lanes will be closed overnight I-94 WB from 124th St to Moorland Rd for mill and fill and staining.

– there will be a full closure overnight I-41/894 NB at National Ave for mill and fill.

– there will be a full closure overnight I-41/894 SB at National Ave for paving.   *contingency is Wednesday 8/22

– the Zoo Int E-N system ramp will be closed overnight for barrier wall work.

– the Zoo Int W-N system ramp will be closed overnight for barrier wall work.

 

Wednesday (8/22)

Zoo Interchange Project

– lanes will be closed overnight I-94 WB from 124th St to Moorland Rd for mill and fill and staining.

– a lane will be closed overnight I-43 NB from 116th St to the Hale Interchange for paving.

– there will be a full closure overnight I-43/894 WB at 76th St for paving.

– there will be a full closure overnight I-41 SB at Watertown Plank Rd for storm sewer work and pavement grinding.

– the Zoo Int E-N system ramp will be closed overnight for storm sewer work and pavement grinding.

– the Zoo Int E-S system ramp will be closed overnight for storm sewer work and pavement grinding.

– the Zoo Int W-N system ramp will be closed overnight for storm sewer work and pavement grinding.

– the Zoo Int W-S system ramp will be closed overnight for storm sewer work and pavement grinding.

– the Hale Int W-N system ramp will be closed overnight for paving.

 

Thursday (8/23)

Zoo Interchange Project

– lanes will be closed overnight I-94 WB from 124th St to Moorland Rd for mill and fill and staining.

– a lane will be closed overnight I-43 NB from 116th St to the Hale Interchange for paving.

– there will be a full closure overnight I-43/894 WB at 76th St for paving.

– there will be a full closure overnight I-41 SB at North Ave for pavement marking.

– the Zoo Int E-N system ramp will be closed overnight for pavement marking.

– the Zoo Int E-S system ramp will be closed overnight for pavement marking.

– the Zoo Int W-N system ramp will be closed overnight for pavement marking.

– the Zoo Int W-S system ramp will be closed overnight for pavement marking.

– the Hale Int W-N system ramp will be closed overnight for paving.

 

Friday (8/24)

Zoo Interchange Project

– lanes will be closed overnight I-94 WB from 124th St to Moorland Rd for mill and fill and staining.

– a lane will be closed overnight I-43 NB from 116th St to the Hale Interchange for paving.

– there will be a full closure overnight I-43/894 WB at 76th St for paving.

– there will be a full closure overnight I-41 SB at North Ave for pavement marking.

– the Zoo Int E-N system ramp will be closed overnight for pavement marking.

– the Zoo Int E-S system ramp will be closed overnight for pavement marking.

– the Zoo Int W-N system ramp will be closed overnight for pavement marking.

– the Zoo Int W-S system ramp will be closed overnight for pavement marking.

– the Hale Int W-N system ramp will be closed overnight for paving.

 

Saturday (8/25)

Zoo Interchange Project

– only long-term closures in effect.

 

Sunday (8/26)

Zoo Interchange Project

– only long-term closures in effect.

 

Long-Term Closures

Zoo Interchange Area Projects

– there will be a full closure of the Beloit Rd entrance ramp to I-41/894 NB through 8/20 for roadway work.

– there will be a full closure of the I-41 NB exit ramp to Bluemound Rd through late August 2018 for ramp reconstruction.

– there will be a full closure of the Greenfield Ave entrance ramp to I-41/894 NB through late August 2018 for ramp reconstruction.

– there will be a full closure of the I-41/894 SB exit ramp to Greenfield Ave through late August 2018 for roadway construction.

– there will be a full closure of the I-41/894 SB exit ramp to Lincoln Ave through late August 2018 for roadway construction.

– there will be a full closure of Schlinger Ave EB/WB under I-41/894 through late August 2018 for project construction.

– the Hank Aaron State Trail will be closed to pedestrians from 94th Pl to Oak Leaf Trail through late August 2018 for project construction

– there will be a full closure of 100th St NB/SB from Walker St to Bungalow Pkwy through August 2018 for roadway work (local access will be maintained).

– there will be a full closure of the 100th St NB/SB and Bungalow Pkwy EB/WB intersection through August 2018 for roadway work (local access will be maintained).

– there will be a full closure of the 100th St NB/SB and Schlinger Ave EB/WB intersection through August 2018 for roadway work (local access will be maintained).

– there will be a full closure of the 100th St NB/SB and Walker St EB/WB intersection through August 2018 for roadway work (local access will be maintained).

– there will be a full closure of the 98th St NB/SB and Schlinger Ave EB/WB intersection through August 2018 for roadway work (local access will be maintained).

– there will be a full closure of the 94th Pl NB/SB at Hank Aaron State Trail through late August 2018 for roadway work.

– there will be a full closure of the 116th St NB/SB and Fairview Ave EB/WB intersection through late August 2018 for roadway work.

– there will be a full closure of Sunnyslope Rd NB/SB over I-94 through late August 2018 for bridge reconstruction.

– a lane will be closed on Watertown Plank Rd EB/WB from HWY 100 to 115th St through early September 2018 for bridge reconstruction.

– a lane will be closed HWY 100 NB/SB and Beloit Rd EB/WB through October 2018 for roadway work.

– a lane will be closed on HWY 100 NB/SB from I-94 to Colder’s Driveway through late October 2018 for bridge work.

– a left-turn lane will be closed on Bluemound Rd WB at HWY 100 through late October 2018 for bridge work.

– there will be a full closure of the I-94 EB exit ramp to HWY 100 SB through late October 2018 for bridge work (access to HWY 100 NB will remain open at all times).