Zoo Interchange Project

Latest Traffic Report: 6/20/18

List of all scheduled closures and restrictions on the Zoo Interchange Project from June 20 – July 1:

Wednesday (6/20)

Zoo Interchange Project

– lanes will be closed overnight I-94 WB from HWY 100 to Moorland Rd for milling and sign removal.

– lanes will be closed overnight I-43/894 WB from Forest Home Ave to the Hale Interchange for barrier wall.

– there will be a full closure overnight I-41/894 SB at National Ave for bridge work, paving, and base patching.

– there will be a full closure overnight I-41 SB at Watertown Plank Rd for stripping.

– there will be a full closure overnight I-94 WB at 84th St for staining.

– the Hale Int E-W system ramp will be closed overnight for barrier wall work and crash cushion work.

 

Thursday (6/21)

Zoo Interchange Project

– lanes will be closed overnight I-41/894 NB from Beloit Rd to National Ave for bridge work.

– lanes will be closed overnight I-43/894 WB from Forest Home Ave to the Hale Interchange for barrier wall and crash cushion work.

– a lane will be closed overnight I-43/894 EB from 92nd St to Forest Home Ave for barrier wall installation.

– a lane will be closed overnight on the Hale Int E-N system ramp for barrier wall work and crash cushion work.

– there will be a full closure overnight I-94 EB at Moorland Rd for a deck pour.   *contingency is Friday 6/22

– there will be a full closure overnight I-41/894 SB at National Ave for bridge work.

– there will be a full closure overnight I-94 WB at 84th St for a deck pour and staining.   *contingency is Friday 6/22

– the Zoo Int N-W system ramp will be closed overnight for a deck pour.   *contingency is Friday 6/22

– the Zoo Int S-W system ramp will be closed overnight for a deck pour.   *contingency is Friday 6/22

– the Hale Int E-W system ramp will be closed overnight for barrier wall work and crash cushion work.

 

Friday (6/22)

Zoo Interchange Project

– there will be a full closure overnight Bluemound Rd EB/WB from 95th St to 98th St for overlay work.   *contingency is Sunday 6/24

– lanes will be closed overnight I-41/894 NB from Beloit Rd to National Ave for bridge work.

– lanes will be closed overnight I-94 EB at 121st St for barrier wall work and pavement marking.   *contingency is Saturday 6/23

– there will be a full closure overnight I-41 SB at Watertown Plank Rd for stripping, barrier wall work, and pavement marking.   *contingency is Saturday 6/23

– there will be a full closure overnight I-41/894 SB at National Ave for a traffic switch.   *contingency is Saturday 6/23

– there will be a full closure overnight I-94 WB at 84th St for painting.   *contingency is Saturday 6/23

– the Zoo Int W-N system ramp will be closed overnight for barrier wall work and pavement marking.   *contingency is Saturday 6/23

– the Zoo Int W-S system ramp will be closed overnight for barrier wall work and pavement marking.   *contingency is Saturday 6/23

 

Saturday (6/23)

Zoo Interchange Project

– the National Ave entrance ramp to I-41/894 SB reopens to traffic by 7am.   *contingency is Sunday 6/24

– the lane closure on I-41/894 SB from National Ave to the Hale Interchange reopens to traffic by 7am.   *contingency is Sunday 6/24

 

Sunday (6/24)

Zoo Interchange Project

– lanes will be closed overnight I-41/894 NB from Beloit Rd to National Ave for barrier wall removal.

– lanes will be closed overnight I-41/894 SB from National Ave to the Hale Interchange for barrier wall installation.

 

Monday (6/25)

Zoo Interchange Project

– a lane will be closed overnight Curtis Rd SB under I-94 for bridge staining.

– there will be a full closure overnight Curtis Rd NB under I-94 for bridge staining.

– a lane will be closed overnight I-41/894 SB from National Ave to the Hale Interchange for barrier wall installation and bridge work.

– lanes will be closed overnight I-43/894 WB from 76th St to 92nd St for barrier wall work.

– lanes will be closed overnight I-41/894 NB from Beloit Rd to National Ave for barrier wall removal and bridge work.

– a lane will be closed overnight I-43 NB from 116th St to the Hale Interchange for barrier wall removal.

– lanes will be closed overnight I-94 EB at HWY 100 for storm sewer work.

– there will be a full closure overnight I-41 SB at Bluemound Rd for barrier wall work and pavement marking.   *contingency is Tuesday 6/26

– there will be a full closure overnight I-94 WB at 84th St for pavement marking.   *contingency is Tuesday 6/26

– the Zoo Int W-N system ramp will be closed overnight for pavement marking.   *contingency is Tuesday 6/26

– the Zoo Int W-S system ramp will be closed overnight for pavement marking.   *contingency is Tuesday 6/26

– the Hale Int N-W system ramp will be closed overnight for barrier wall work and bridge work.

– the Hale Int W-N system ramp will be closed overnight for barrier wall removal.

 

Tuesday (6/26)

Zoo Interchange Project

– the 84th St entrance ramp to I-94 WB to I-41 NB access will be restored by 5am.   *contingency is Wednesday 6/27

– the 84th St entrance ramp to I-94 WB to I-41/894 SB access will be restored by 5am.   *contingency is Wednesday 6/27

– the Zoo Int E-S system ramp reopens by 5am.   *contingency is Wednesday 6/27

– a lane will be closed overnight Curtis Rd SB under I-94 for bridge staining.

– there will be a full closure overnight Curtis Rd NB under I-94 for bridge staining.

– lanes will be closed overnight I-43/894 WB from 76th St to 92nd St for barrier wall work.   *contingency is Wednesday 6/27

– lanes will be closed overnight I-41/894 NB from Beloit Rd to National Ave for barrier wall removal and bridge work.

– lanes will be closed overnight I-41/894 SB from National Ave to the Hale Interchange for barrier wall installation.

– a lane will be closed overnight I-43 NB from 116th St to the Hale Interchange for barrier wall removal.   *contingency is Wednesday 6/27

– there will be a full closure overnight I-94 EB at the Zoo Interchange for storm sewer work.

– the Hale Int N-W system ramp will be closed overnight for barrier wall work and bridge work.   *contingency is Wednesday 6/27

– the Hale Int W-N system ramp will be closed overnight for barrier wall removal.   *contingency is Wednesday 6/27

 

Wednesday (6/27)

Zoo Interchange Project

– a lane will be closed overnight Curtis Rd SB under I-94 for bridge staining.

– there will be a full closure overnight Curtis Rd NB under I-94 for bridge staining.

– a lane will be closed overnight I-41/894 NB from Howard Ave to National Ave for barrier wall removal and bridge work.

– a lane will be closed overnight I-41/894 SB from National Ave to the Hale Interchange for barrier wall installation and bridge work.

– there will be a full closure overnight I-94 EB at the Zoo Interchange for storm sewer work.

 

Thursday (6/28)

Zoo Interchange Project

– Coldspring Rd EB/WB from 92nd St to HWY 100 reopens to traffic by 5am.

– there will be a full closure overnight I-94 EB at the Zoo Interchange for storm sewer work.

 

Friday (6/29)

Zoo Interchange Project

– a lane will be closed overnight I-43 NB from 116th St to the Hale Interchange for a traffic switch and barrier wall work.   *contingency is Saturday 6/30

– the Hale Int W-N system ramp will be closed overnight for a traffic switch and barrier wall work.   *contingency is Saturday 6/30

– there will be a full closure overnight I-94 EB at the Zoo Interchange for storm sewer work.

 

Saturday (6/30)

Zoo Interchange Project

– only long-term closures in effect.

 

Sunday (7/1)

Zoo Interchange Project

– only long-term closures in effect.

 

Long-Term Closures

Zoo Interchange Area Projects

– there will be a full closure of the National Ave entrance ramp to I-41/894 SB through 6/23 for roadway work.

– a lane will be closed on I-41/894 SB from National Ave to the Hale Interchange through 6/23 for roadway work.

– there will be a full closure of the 84th St entrance ramp to I-94 WB (to I-41 NB) through 6/26 for roadway reconstruction.

– there will be a full closure of the 84th St entrance ramp to I-94 WB (to I-41/894 SB) through 6/26 for roadway reconstruction.

– there will be a full closure of the Zoo Int E-S system ramp through 6/26 for ramp reconstruction.

– there will be a full closure of Coldspring Rd EB/WB from 92nd St to HWY 100 through 6/28 for bridge painting.

– there will be a full closure of the I-94 EB exit ramp to 84th St (from I-94 EB) through late July 2018 for roadway reconstruction.

– there will be a full closure of the I-41 NB exit ramp to Bluemound Rd through early Summer 2018 for ramp reconstruction.

– there will be a full closure of the Greenfield Ave entrance ramp to I-41/894 NB through early Summer 2018 for ramp reconstruction.

– there will be a full closure of the I-41/894 SB exit ramp to Greenfield Ave through early Summer 2018 for roadway construction.

– there will be a full closure of the I-41/894 SB exit ramp to Lincoln Ave through early Summer 2018 for roadway construction.

– there will be a full closure of 100th St NB/SB from Walker St to Bungalow Pkwy through August 2018 for roadway work (local access will be maintained).

– there will be a full closure of the 100th St NB/SB and Bungalow Pkwy EB/WB intersection through August 2018 for roadway work (local access will be maintained).

– there will be a full closure of the 100th St NB/SB and Schlinger Ave EB/WB intersection through August 2018 for roadway work (local access will be maintained).

– there will be a full closure of the 100th St NB/SB and Walker St EB/WB intersection through August 2018 for roadway work (local access will be maintained).

– there will be a full closure of the 98th St NB/SB and Schlinger Ave EB/WB intersection through August 2018 for roadway work (local access will be maintained).

– there will be a full closure of Sunnyslope Rd NB/SB over I-94 through late August 2018 for bridge reconstruction.

– there will be a full closure of Schlinger Ave EB/WB under I-41/894 through late Summer 2018 for project construction.

– the Hank Aaron State Trail will be closed to pedestrians from 94th Pl to Oak Leaf Trail through late Summer 2018 for project construction.

– a lane will be closed on HWY 100 SB from I-94 to Colder’s Driveway through late Summer 2018 for bridge work.

– a left-turn lane will be closed on Bluemound Rd WB at HWY 100 through late Summer 2018 for bridge work.

– there will be a full closure of the I-94 EB exit ramp to HWY 100 SB through late Summer 2018 for bridge work (access to HWY 100 NB will remain open at all times).

– a lane will be closed on Watertown Plank Rd EB/WB from HWY 100 to 115th St through early September 2018 for bridge reconstruction.