WIS 80 (Liberty Street to WIS 82)

Elroy, Juneau County

Traffic impacts/detour routes

*The schedule is subject to change.

Stage 1: WIS 71 to CTY PP

(March to mid-August)

  • WIS 80 will be detoured and closed to through traffic.
    • Access for local, business, and emergency traffic will be maintained at all times with a minimum base aggregate surface except when the contractor is working in the immediate area.
    • Detour route is shown in the traffic control overview below.
    • May 21, 2020 – 2 week look ahead

Stage 2: Liberty Street to WIS 71

(mid-August to mid-September)

  • WIS 80 will be constructed in stages and remain open to traffic.

Stage 3: CTY PP to Kimball Avenue

(mid-September to November)

  • WIS 80 will be constructed in stages and remain open to traffic.

Stage 4: Kimball Avenue to WIS 82

(start of November to mid-November)

  • WIS 80 will have a single lane closure with flagging operations.

View traffic control overview