WIS 66 Stevens Point

WIS 66/Main Street, Plover River Bridge at Iverson Park

Traffic Impacts & Schedule

The eight-foot wide shared use path on eastbound side of bridge will not be impacted with this project. Construction dates are dependent upon favorable weather conditions.

Stage 1: (July 15-19)

Traffic on WIS 66 will be reduced to one, 11 foot maximum width lane in each direction. The speed limit will be reduced from 40 mph to 30 mph.

Stage 2: (July 19- Aug 26)

Traffic will be diverted to the eastbound lanes with unidirectional traffic. The traffic lanes will be reduced to a maximum 11 foot lane and the speed limit will be reduced from 40 mph to 30 mph thru the construction zone.

Stage 3: (Aug 26 – 29)

Traffic on WIS 66 will be reduced to one, 11 foot maximum width lane in each direction. The speed limit will be reduced from 40 mph to 30 mph.

Stage 4 and 5: (Sept. 12 – 27)

Traffic on westbound WIS 66 will be reduced to one, 11 foot maximum width lane and the speed limit will be reduced from 40 mph to 30 mph.