The 2021 construction schedule is:

  • Start: April 26, 2021
  • Completion: November 2021

Construction will be completed in segments. Here is the tentative schedule for work and the related traffic impacts.

  • The detour will use I-94, Minnesota Trunk Highways 95 and 36 and WIS 64.

Hudson

Front Street to Vine Street

  • Construction: April 26 to June 14 and June 22 to July 10
  • Traffic impact: Road open to one lane of traffic in each direction.
    • This segment will be completely open during the Fourth of July weekend.
  • Pedestrian access: Pedestrians will be accommodated throughout the project.

Vine Street to south of Myrtle Street

  • Construction: July 13 to Sept. 7
  • Traffic impact: Road closed.
    • The contractor will maintain evening access to properties when possible.
  • Pedestrian access: Pedestrians will be accommodated throughout the project.

South of Myrtle Street to south of Division Street

  • Construction: April 26 to July 13
  • Traffic impact: Road closed.
    • The contractor will maintain daily drivable access to the Croix View Apartments from 11 a.m. to 1 p.m. and 4 to 6 p.m. for meal services.
      • The contractor will provide 72-hour written notice to the assisted-living facility manager for temporary driveway closure. The notice will include duration of the closure.
    • The contractor will maintain evening access to properties when possible.
  • Pedestrian access: Pedestrians will be accommodated throughout the project.

Hudson to North Hudson

South of Division Street to north of South Street

  • Construction: Sept. 7 to Nov. 20
  • Lake Mallalieu Bridge: Because of work at the South and North street intersections, the bridge will be closed from Sept. 13 to 25. These dates more than likely will change.
  • Traffic impact: This section will be built using staged construction, including short-term full closures and temporary signals controlling a single lane of traffic.
    • Stage 1:
      • Traffic impact: The WIS 35 intersections at Division and North streets in Hudson will be closed.
        • Roadway closures to complete the work at both intersections should not exceed seven calendar days.
        • The contractor shall provide a minimum 10-foot-wide access at all homes west of the intersections.
      • Pedestrian access: Pedestrians will be accommodated throughout the project.
    • Stage 2:
      • Traffic impact: The WIS 35 intersection at South Street in North Hudson will be closed.
      • The roadway closure to complete the work should not exceed seven calendar days.
      • Pedestrian access: Pedestrians will be accommodated throughout the project.
    • Stage 3:
      • Traffic impact: A single lane of traffic will be maintained on northbound WIS 35 from Division Street in Hudson to South Street in North Hudson with the use of temporary signals.
        • The WIS 35 intersections at Division and North streets in Hudson will not be fully closed and will require paving gaps to allow for residential access.
        • The contractor will provide temporary access to residential driveways when imminent work is not being completed.
      • Pedestrian access: Pedestrians will be accommodated throughout the project.
    • Stage 4:
      • Traffic impact: A single lane traffic will be maintained on southbound WIS 35 from Division Street in Hudson to South Street in North Hudson with the use of temporary signals.
        • WIS 35 north of South Street to Wisconsin Street North will remain closed through this stage.
      • Pedestrian access: Pedestrians will be accommodated throughout the project.

North Hudson

North of South Street to south of Monroe Street North

  • Construction: Aug. 17 to Oct. 4
  • Traffic impact: Road closed.
    • The WIS 35 intersections at Wisconsin Street North and Monroe Street North shall not be closed at the same time.
    • The contractor will maintain evening access to properties when possible.
  • Pedestrian access: Pedestrians will be accommodated throughout the project.

South of Monroe Street North to Michaelson Street North

  • Construction: May 3 to July 17
  • Traffic impact: Road closed.
    • The contractor will maintain evening access to properties when possible.
  • Pedestrian access: Pedestrians will be accommodated throughout the project.

Michaelson Street North to North End Road

    • Construction: July 17 to Sept. 23.
    • Traffic impact: It will vary by segment.
      • The road will be closed from Wisconsin Street North and Sommers Street.
      • WIS 35 from Sommers Street to North End Road shall remain open to a single lane of traffic with the use of flagging.
      • The contractor will maintain evening access to properties when possible.
    • Pedestrian access: Pedestrians will be accommodated throughout the project.