WIS 29, Clark County Line to County E

Clark County line to County E

Schedule

Overall schedule: May 26, 2020 to August 25, 2020

Construction will occur during the 2020 construction season and will take approximately 3-1/2 months to complete.

Construction will be completed in several stages.  Repairs will begin on the median lanes and is expected to last 5 weeks. Work will then shift to the outside lanes and will take approximately 5 weeks. Once work is completed on WIS 29, ramp improvements will occur. Ramp improvements will take approximately 4 weeks to complete.