WIS 27 Hayward

Highway Resurface, Restructure, and Maintenance

Schedule

Schedule

March 25, 2019 to June 28, 2019 and September 3, 2019 to November 1, 2019
*This schedule is subject to change depending on weather events and other various circumstances.

Traffic Impacts

During the second stage of the project, WIS 27 will be reduced to one lane in each direction with a posted detour for truck traffic. The detour route will utilize WIS 27, WIS 77 and County K.