WIS 23 bridge over the Wisconsin River

Between Mineral Point & Spring Green, Sauk County

Overview

Construction has resumed for the WIS 23 bridge across the Wisconsin River between Iowa and Sauk County. Boater information

Traffic impacts:

  • Bridge remains closed and traffic is detoured.
  • Bridge anticipated to reopen to traffic in mid-June 2021.
    • At that time, one lane will be open and traffic signals will alternate traffic between northbound/southbound vehicles.
  • Construction completion and bridge fully open to traffic in late September 2021.