WIS 22 Resurfacing, Shawano

Resurfacing of WIS 22 from County B to Zingler Road, Main Street to County BE

Schedule

As of May 7, 2020:

Traffic impacts: Single lane closures both directions on WIS 22 between Airport Road and Ash Court (May 6th – May 15th). Occasional flagging operations on WIS 22 between Rusch Road and Ash Court. Rusch Road and Madison Way will close at WIS 22 during paving operations (Anticipated May 7 and May 8).

Anticipated work scheduled for next week: Crews will place gravel shoulders on WIS 22 between Airport Road and Ash Court, remove all temporary erosion control devices from project, install final pavement marking on WIS 22 from Airport road to Ash Court and conduct project cleanup.