US 10 Bridge Replacement

WIS 22 interchange through Churchill street interchange

Traffic Impacts & Schedule

Traffic Impacts

  • County E, under US 10, will be closed for approximately five months (March 2020 through July 2020). The closure allows crews to safely remove the current bridge and expedites the timeline for the construction of the new bridge.
  • US 10 will remain open to a minimum of one lane of traffic in each direction during construction. Motorists can expect to encounter lane closures, lane shifts (via median crossovers or temporary lanes) and reduced speeds (March 2020 through June 2020).

Schedule

  • Fall 2019 to mid-August 2020
  • Construction-related traffic impacts and schedules are subject to change and are dependent on favorable weather conditions and construction progress.