US 51, Woodruff/Arbor Vitae

US 51, Woodruff/Arbor Vitate, 3rd Avenue to Tuckaway Drive

Photo Gallery

July 10, 2019

July 10, 2019

Storm sewer crew backfilling structure

May 15, 2019

May 15, 2019

Prior to traffic switch

May 15, 2019

May 15, 2019

Prior to traffic switch

May 8, 2019

May 8, 2019

Finished Slope By Brandy Lake Boat Landing

May 8, 2019

May 8, 2019

Crews Paving Parking Lots

April 30, 2019

April 30, 2019

Crews pouring new sidewalk

April 24, 2019

April 24, 2019

Crews Preparing Base Aggregate And Inlets For Curb & Gutter

April 12, 2019

April 12, 2019

April 19, 2019

April 19, 2019

Crews Removing Old Road

April 9, 2019

April 9, 2019

April 3, 2019

April 3, 2019

Removal Of Old Highway In Progress

April 2, 2019

April 2, 2019

Sawing The Highway And Driveway For Removals

April 1, 2019

April 1, 2019

Traffic Reduced To One Lane In Each Direction

March 28, 2019

March 28, 2019

Aeriel View Before Spring Phase

September 5, 2018

September 5, 2018

August 21, 2018

August 21, 2018

August 15, 2018

August 15, 2018

August 7, 2018

August 7, 2018

July 27, 2018

July 27, 2018

Crews excavating at Oak Street in preparation for new gravel.

June 21, 2018

June 21, 2018

Paving first layers of asphalt.

June 18, 2018

June 18, 2018

Preparing for asphalt paving

June 14, 2018

June 14, 2018

June 14, 2018

June 14, 2018

June 1, 2018

June 1, 2018

Crews installing new sidewalk.

May 31, 2018

May 31, 2018

Check out the new curb and gutter. Nice!

May 9, 2018

May 9, 2018

Installing a new culvert near Tuckaway Drive.

April 30, 2018

April 30, 2018

Crews installing sanitary sewer.

April 27, 2018

April 27, 2018

Crews working on sanitary sewer by 3rd Avenue.

April 27, 2018

April 27, 2018

Preparing traffic control at the US 51/WIS 47 intersection.

April 18, 2018

April 18, 2018

April 18, 2018

April 18, 2018

April 18, 2018

April 18, 2018

April 16, 2018

April 16, 2018

(Yes. April.)

April 4, 2018

April 4, 2018