US 45 (Racine County)

_

Traffic Impacts

Stage 1

  • Full closure from just¬†north of 7th Ave. (near Union Grove High School) to just north of Church Road (open only to local traffic).
    • Closures scheduled from May 23 to fall 2017
      • Four-week closure beginning August 21, US 45 will be closed to all traffic at 500 feet north of the high school.
  • Full closure of County C at US 45 ¬†(open only to local traffic)
    • Closures scheduled from May 23 to fall 2017

Stage 2

  • Full closure of US 45 from just north of Church Road to WIS 20
  • Closure scheduled from spring 2018 to fall 2018

Detour

Motorists wishing to bypass the construction are encourage to use the official detour on WIS 75, accessing it by way of WIS 20 or WIS 11. As the closure of County C is limited to near US 45, motorists wishing to accessing businesses in that area are encouraged to use County C, rather than US 45, whenever possible.

For more information about what businesses can do during construction, click here.