*Due to inclement weather, work was not completed this year.

  • Construction work will carry over into Spring 2020
    • Work will be stopped during Winter Months and all roadways will be open to traffic

Upcoming work:

  • US 151/WIS 23 Interchange
    • Expected to be completed late November 2019, weather pending
  • All work on US 151 between WIS 23 and US 18
    • Expected to be completed by mid-December 2019

Finished Work:

  • US 18/151 interchange was completed September 2019