US 12 Bridge Over Wisconsin River

Dane and Sauk Counties

Schedule

  • Construction start date: September 9, 2019
  • Expected completion date: November 8, 2019

Note: Work is suspended during winter months. Completion expected in spring 2020.

Past (prior to today)

  • February 27th, 2019 – Public involvement meeting (PIM)

Expected construction activities

  • Fall 2019 – Joint replacement
  • Spring 2020 – Polymer overlay