Various Bridge Work Locations

Region Wide

Waukesha/Walworth Counties

project overview

Waukesha County

WIS 145 over abandoned railroad in Menomonee Falls

  • Bridge deck overlay
  • Work is anticipated to take place from mid July through the beginning of August 2020. During construction,  a full closure will be in place with a posted detour.

WIS 83 over the Bark River in Hartland

  • Concrete bridge deck overlay
  • Work is anticipated to begin mid August and be complete by mid September 2020. During construction, a full closure near the bridge will be in place with a posted detour.

WIS 83 over the Mukwonago River in Mukwonago

  • Concrete bridge deck repair and overlay
  • Bridge approach pavement overlay
  • Preliminary bridge work is taking place as of June 17, and bridge deck repairs are anticipated to begin mid July. During construction, a full closure of WIS 83 over the Mukwonago River will be in place and a detour posted.

WIS 59 Westbound over the Fox River

  • Concrete bridge deck overlay
  • Work is anticipated to begin early June and be complete in mid July 2020. Bridge repairs will be done in stages and traffic control will be implemented by flagging.

Walworth County
WIS 50 over Jackson Creek in Delavan

  • Concrete bridge deck overlay.
  • Preliminary prep work is anticipated to begin June 10. Construction on the WIS 50 bridge over Jackson Creek is anticipated to begin EARLY July.

WIS 120 over Sugar Creek in Spring Prairie/Elkhorn

  • Bridge deck repair and overlay
  • Work is anticipated to begin May 4, and will be complete late spring 2020. During construction a full road closure will be in place with a posted detour.