Various Bridge Work Locations

Region Wide

Milwaukee/Kenosha Counties

Project overview

Milwaukee

Wells Street over WIS 175 in the City of Milwaukee

  • Work includes the application of crack sealant
  • Work is tentatively scheduled to be done in the span of two days with a full closure the beginning of September 2020.

County BB/W Rawson Avenue westbound over WIS 36/Loomis Road in the Town of Franklin

  • Concrete overlay and painting
  • Work will begin mid April and is anticipated to finish mid June 2020. Traffic impacts are to be expected while crews are working.

County BB/W Rawson Avenue eastbound over WIS 36/Loomis Road in the Town of Franklin

  • Concrete overlay
  • Work is anticipated to begin mid to late April and be complete mid June 2020. Traffic impacts are to be expected while crews are working.

Kenosha

WIS 165 eastbound over Des Plaines River

  • Concrete overlay
  • Work is anticipated to begin late March and be complete in late spring 2020. Traffic will be staged throughout the duration of the project.

WIS 165 over the SOO Line Railroad

  • Bridge deck overlay
  • Work will likely begin mid April and be complete by early June 2020. Traffic impacts are to be expected.