I-94 North-South Freeway Project

WIS 20 Crossroad project – early 2020

The following work is scheduled for the next phase of the project. Click HERE to view more information.

April 2020

Monday, April 13:

• Long-term westbound lane closure of WIS 20,  between International Drive and East Frontage Road, is scheduled to occur at 6 a.m.

Wednesday, April 15:

• WIS 20, between County C/Spring Street and West Frontage Road, is scheduled to close at 6 a.m. through fall 2020.

Detour route: Motorists should utilize County C/Spring Street and County V to get around the WIS 20 closure.

• Access to businesses and residences between County C/Spring Street and West Frontage Road will be maintained via Greenmonte Drive.

• Access to businesses located on Spokes Circle will be maintained via West Frontage Road.

• Access to businesses located at the WIS 20 interchange will remain open from the east.