I-94 North-South Freeway Project

Seven Mile Road Interchange Scheduled to Open

The following work is scheduled for the next phase of this project.

Wednesday, May 6:
• Seven Mile Road, under I-94, is scheduled to open to traffic by 6 a.m.
• The I-94 entrance/exit ramps, at Seven Mile Road, are scheduled to open to traffic by
6 a.m.
Access restrictions at Seven Mile Road:
• Access to/from West Frontage Road (south of Seven Mile Road) will be restricted to
right-turn only movements early May through mid-May.
• Access to/from East Frontage Road will be restricted to right-turn only movements
mid-May through late May.
• Access to/from Stanley Road and Hagemann Road will be restricted to right-turn only
movements early May through late May.

Seven Mile Road will remain under construction through late spring 2020.

Please note that all work is weather dependent and subject to change.