I-94 North-South Freeway Project

Bridge Maintenance Project

Overview

This project will implement preventative maintenance at multiple bridge locations along I-41/I-94 in Kenosha and Racine counties. A protective Thin Polymer Overlay (TPO) will be applied to bridges located between the Des Plaines River and the northern Racine County Line.

Location

Milwaukee County

  • I-94 over the Root River
  • Elm Road over I-94
  • I-94 over Oakwood Road
  • I-94 over Oak Creek (just south of Ryan Road)
  • Ryan Road entrance ramp to I-94 southbound over Oak Creek
  • Ryan Road exit ramp from I-94 northbound over Oak Creek
  • Ryan Road over I-94
  • I-94 culvert just south of Drexel Avenue

Racine County

  • I-94 over Braun Road
  • I-94 over WIS 11
  • I-94 over 58th Road
  • I-94 over WIS 20
  • County C over I-94
  • I-94 over Kraut Road
  • I-94 over Golf Road
  • I-94 over County K
  • County G over I-94
  • I-94 over 7 Mile Road
  • I-94 culvert over Kilbourn Road Ditch
  • I-94 culvert over Root River

Kenosha County

  • I-94 over the Des Plaines River
  • I-94 over WIS 50
  • I-94 over 71st Street
  • I-94 over 60th Street
  • I-94 over WIS 158
  • I-94 over 38th Street
  • I-94 over WIS 142
  • I-94 culvert over Kilbourn Road Ditch
  • I-94 over County E
  • I-94 over County A
  • I-94 over County KR

Project improvements

Thin Polymer Overlays are used to seal the road surface of the bridge and prevent salt from leaching down into steel reinforcement. A TPO is a thin coat of polymer spread across the deck in two coats with aggregate applied between each coat. They are typically applied within the first ten years of initial bridge construction to preserve structural integrity.

schedule

Work is scheduled to begin the week of June 7 and be complete by late summer, 2021.

traffic impacts

To help minimize traffic impacts, all temporary lane restrictions or ramp closures are scheduled to occur during off-peak travel times and overnight hours. Intermittent, overnight detours will be posted.