I-90/94 and WIS 82 interchange

Mauston – Juneau County

Traffic impacts


Download the I-90/94 project update – March 20, 2022

I-90/94:

Four lanes of traffic (two lanes in each direction) will be maintained on I-90/94 during construction. Temporary roadway and temporary bridge structures within the I‐90/94 median will be utilized to maintain traffic. During isolated short-term periods, reduction to one lane in each direction will be required using nighttime lane closures.

WIS 82:

Two lanes of traffic (one lane in each direction) will be maintained on WIS 82. Isolated short-term nighttime closures is expected for bridge work over WIS 82. Detour routes will utilize I-90/94 to New Lisbon and Lyndon Station.

Access to adjacent businesses will be maintained throughout construction.