I-43/I-94 Valley Bridges

Milwaukee County

Construction updates

The following is a summary of anticipated upcoming closure schedules. Please note this schedule is weather dependent and subject to change.

Click here for a map overview of anticipated ramp closures and detours from March to early May.

Wednesday Night (2/28)

  • I-94 East to I-43 South full closure until late July
  • I-794 West to I-43 South full closure until late June
  • 11th Street and Wisconsin Avenue entrance ramp to I-43 South full closure until late May

Friday Night (3/2)

  • 6th Street/Mineral Street entrance ramp to I-43 North full closure until late August
  • 9th Street/Walker Street entrance ramp to I-43 North full closure until late August
  • I-43 North exit ramp to I-794 East full closure until early May
  • I-43 North exit ramp to Plankinton Avenue full closure until early May
  • I-43 North lane closure until late July

Monday (3/5)

  • I-43 South lane closure until late July

Future closures

  • I-43 North ramp to I-94 West will close early¬†May through late June
  • I-43 North ramp to Michigan Avenue¬†/ 10th Street will close early May through late June

Primary detour route for the I-43 North to the East and I-794 West to the South is the Hoan Bridge.