Wisconn Valley Development Roads

Racine County

Project Overview

WisDOT is working with the Village of Mount Pleasant and Racine County on the reconstruction of several state, village and county roadways around the new Foxconn Development in Racine County.

Wisconn Valley Roadways Construction

Sign up for e-mail construction update under the Additional Resources tab.

  • County KR (between East Frontage Road and County H)
    • County KR, between East Frontage Road and County H, will be expanded to a six-lane concrete roadway. Construction of the new westbound lanes, to the north of the existing roadway, is scheduled to start early April. One lane of traffic will remain open in each direction on the current roadway. All lanes of traffic on County KR are scheduled to be open by late 2019. READ MORE
  • County H (County KR and Braun Road)
    • Work began in mid March to reconstruct County H to a four-lane concrete roadway. All newly reconstructed County H lanes are scheduled to be open by spring 2020.  Access to residences and businesses will be maintained. The speed limit will be reduced to 35 mph from south of County KR to WIS 11 during construction. READ MORE
  • Braun Road (I-94 to 90th Street)
    • The project began in August 2018 to reconstruct Braun Road to a six-lane urban roadway with concrete pavement between I-94 and County H. Braun Road is closed to motorists until fall 2019. Access will be maintained for emergency vehicles and contractor traffic.
    • Construction highlights
  • International Drive (South limit to WIS 11)
    • The project began in August to construct International Drive, a new four lane concrete roadway connecting WIS 11 to WIS 20.  Construction is anticipated to be complete late fall 2019.
    • Construction highlights
  • WIS 11 and Willow Road intersection 

Wisconn Valley Roadways Design

*Large files may take a moment to download.

 Jurisdictional Transfer Process

In November 2017, WisDOT took temporary jurisdiction over several local roadways. The temporary assigned jurisdiction of these local roads was granted to WisDOT because of the department’s experience in delivering complex roadway projects that require coordinating aggressive delivery schedules. After reconstruction is complete, local jurisdiction will resume.

Additional Project Information

Schedule

Summer 2018 to fall 2021

I-94 North/South

Interested in the activity along the I-94 North/South project? Click here for more information. >> I-94 North/South project