Wisconn Valley Development Roads

Racine County

Project Overview

WisDOT is working with the Village of Mount Pleasant and Racine County on the reconstruction of several state, village and county roadways around the new Foxconn Development in Racine County.

Wisconn Valley Roadways Construction

View the weekly construction update under the Additional Resources tab.

  • *NEW* County H (County KR and Braun Road)
    • Work begins in mid March to reconstruct County H to a four-lane concrete roadway. All newly reconstructed County H lanes are scheduled to be open by spring 2020.  Access to residences and businesses will be maintained. The speed limit will be reduced to 35 mph from south of County KR to WIS 11 during construction. READ MORE
  • Braun Road (I-94 to 90th Street)
    • The project began in August 2018 to reconstruct Braun Road to a six-lane urban roadway with concrete pavement between I-94 and County H. Braun Road is closed to motorists until fall 2019. Access will be maintained for emergency vehicles and contractor traffic.
    • Construction highlights
  • International Drive (South limit to WIS 11)
    • The project began in August to construct International Drive, a new four lane concrete roadway connecting WIS 11 to WIS 20.  Construction is anticipated to be complete late fall 2019.
    • Construction highlights
  • WIS 11 and Willow Road intersection 

Wisconn Valley Roadways Design

  • WIS 11 (56th Road to County H)
  • County H (County KR to Venice Avenue – north of WIS 11)
  • County KR (I-94 to Old Green Bay Road)
    • Handout (public information meeting – Oct. 18, 2018)
    • Handout (public information meeting – July 12, 2018)
    • Aerial Plot (west segment)
    • Aerial Plot (east segment)
    • View the environmental document
  • Braun Road (I-94 to 90th Street)
  • Wisconn Valley Way (County KR to WIS 11)
  • International Drive (South limit to WIS 11)

*Large files may take a moment to download.

 Jurisdictional Transfer Process

In November 2017, WisDOT took temporary jurisdiction over several local roadways. The temporary assigned jurisdiction of these local roads was granted to WisDOT because of the department’s experience in delivering complex roadway projects that require coordinating aggressive delivery schedules. After reconstruction is complete, local jurisdiction will resume.

Additional Project Information

Schedule

Summer 2018 to fall 2021

I-94 North/South

Interested in the activity along the I-94 North/South project? Click here for more information. >> I-94 North/South project