I-41 and WIS 175 - Bridges and Culverts

Washington County

Traffic Impacts

Traffic on I-41 northbound will be reduced by two (2) lanes to a single lane in two (2) stages at each structure location between County Line Road/County Q to Holy Hill Road/WIS 167 westbound. Traffic control will not occur on consecutive bridges on I-41.

Traffic on I-41 southbound traffic will be reduced by two (2) lanes to a single lane in two (2) stages at each structure location between County Line Road/County Q to Holy Hill Road/WIS 167 westbound. Traffic control will not occur on consecutive bridges on I-41.

Traffic on I-41 northbound will be reduced to a single lane in two (2) stages at each structure located at US 45 and WIS 60.

Traffic on I-41 southbound traffic will be reduced to a single lane in two (2) stages at each structure located at US 45 and WIS 60.

Local bridge closures will occur at Maple Road, Mequon Road and Freistadt Road. Bridge closures will be staged to occur at different times through construction.

Traffic on eastbound County Line Road/County Q will be closed to local traffic in a single stage. Traffic on westbound County Line Road/County Q will be closed to local traffic in a separate stage.

I-41 entrance and exit ramp movements will altered at County Line Road/County Q and Holy Hill Road/WIS 167 locations during traffic control staging.

Overnight local bridge closures will occur at County Line Road/County Q and Holy Hill Road/WIS 167.

Overnight work and interstate/ramp closures