WIS 16/La Crosse St (West Ave to Losey Boulevard)

City of La Crosse, La Crosse County

Traffic impacts

The project will be constructed in three segments, moving from west to east: WIS 35/West Avenue to East Avenue; East Avenue to Hillview Avenue; and Hillview Avenue to Losey Boulevard.

La Crosse Street will be closed to through traffic between West Avenue and East Avenue during the first stage of construction, which is expected to last approximately two months. Access to businesses and residences will remain open. Through traffic will be detoured using Main Street.

Access to Myrick Park and the La Crosse Marsh trails system will remain open throughout the project. During the first stage, access to the park will use Myrick Park Drive. The second stage will use 22nd and 23rd streets. The final stage will use Myrick Park Drive. Myrick Park will also be accessible from Losey Boulevard for a majority of the project.

Construction is currently scheduled for completion by May 2023. La Crosse Street will be open to normal traffic operations from December until completion work in the spring of 2023. The schedule is dependent on favorable weather conditions and construction progress.